Turn an unexpected condition into a documented next decision.

Record the finding, evidence, safe temporary condition, options, scope effect, authorization, follow-through, and closeout without overstating what was discovered.

Opening a repair area can reveal a different wall layer, wider unsound material, another trade interface, or a condition outside the original assumption. The response should preserve facts and authority rather than rely on a phone-call memory.

Record the finding precisely

Identify the location, date, original assumption, observable condition, photographs or measurements actually taken, work paused, and immediate protection. Avoid labels such as “structural failure,” “code violation,” “mold,” or “waterproofing failure” unless the qualified basis exists. State the limit of what was exposed and what remains concealed. Notify the designated representative using the agreed channel and protect the area consistent with actual site and contract requirements.

Develop bounded options

Describe the option, responsible trade, additional access, materials or layers affected, finish-boundary effect, schedule or occupied-use impact, outside review needed, exclusions, and what remains unknown. One option may be further evaluation rather than construction. Do not treat an allowance as approval. Where a safe temporary condition or weather protection is needed, identify that separately from the permanent recommendation and obtain direction under the applicable agreement.

Capture authorization and field follow-through

Record the authorized option, approver, date, method, revised repair map or scope, price and schedule document when applicable, and people notified. Give the field lead a current written direction before changed work proceeds. After the work, record what was actually completed, testing or review applicable to that work, remaining exclusions, and the release for the next stage. A closed wall should not erase the decision history.

Example: vague versus usable

“Found more damage; owner approved repair” does not explain location, evidence, extent, option, or authority. A usable record says that removal at the marked area exposed additional loose material to a documented boundary; work paused and the area was protected; photos and an updated repair map were reviewed; the named representative authorized the stated extension and finish effect through the identified written change; other concealed areas and root cause remained unverified.

Use the worksheet and close the loop

Create one row per finding with record number, location, original assumption, observed fact, evidence, exposure limit, temporary condition, options, specialist question, scope/finish/schedule effect, authorized decision, approver/date, field completion, next-stage release, and recipients. Link the final record to closeout photos and punch items. At project closeout, list unresolved or excluded conditions plainly so a completed cosmetic surface is not mistaken for evaluation of the entire wall.

Concealed-condition and change register

Use one copy per verified area or decision. Keep the current version with the approved scope.

Record ID
________________
Location
________________
Original assumption
________________
Observed fact
________________
Evidence
________________
Exposure limit
________________
Temporary condition
________________
Options
________________
Scope effect
________________
Decision
________________
Approver/date
________________
Completion
________________
Next release
________________
Recipients
________________
Download blank CSV worksheet

Approval checklist

  • Exact location
  • Observed facts
  • Evidence
  • Limit of exposure
  • Safe paused condition
  • Bounded options
  • Written authorization
  • Updated field direction
  • Completion record
  • Remaining exclusions

Before approval

Questions to resolve

Is an allowance approval of any added work?

No. An allowance and an authorization should be applied according to the written agreement and actual changed condition.

Can the contractor name every concealed condition?

No. Record only what is supported by the exposed area and appropriate qualified review.

What belongs in closeout?

The decision record, approved change, completed work, applicable stage release, photos when appropriate, and unresolved or excluded items.

Verified AWC resources

Related field and planning context

Company guidance and field context; not evidence about another property.

Start with a conversation

Tell us what you see.
We’ll help define the next step.

Coronado · Stucco · AWC